Work on Ahmedabad Urban Development Authority’s EWS housing units at various locations in Ahmedabad district of Gujarat on BOT basis is underway. The authority has finalised contractors for these housing units, for which bids were invited in March 2006.

Location

Housing units

Contractor

Status

Completion

Vastral

1,100

Syntex

 

Underway

 

December 2009

Vastral,Bodakdev

1,120 and 2,368

Khurana Constructions

December 2009

Niko area

2,240

Ranjit Constructions

December 2010

The project will entail an investment of Rs.120 crore, of which 50 per cent of the project will be funded through Central government, 30 per cent by internal accruals and remaining 20 per cent by state government.