Work on double-decker highway in Kenya to begin in September 2019Illustrative image – not actual.
Construction work on the first double-decker highway road in Nairobi, Kenya, is set to begin in September 2019. The double-decker road project is set to link Jomo Kenyatta International Airport (JKIA) to the Nairobi-Nakuru highway.

The project has been delayed for nearly a decade with the first attempt collapsing after the World Bank questioned its suitability and cut financing.

The project was approved in 2008. It involves construction of 77 km double-decker road in Nairobi under a 30-year build, operate, transfer deal that allows private firms to invest in a public project and operate it for an agreed period to recoup their investment and profit before handing it over to the state.

Construction work will take two years at an estimated cost of USD 494 million. The proposed elevated dual carriageway is to be built in three phases beginning with the first 6.5 km running from JKIA to Likoni Road and the Southern Bypass interchange.

A bus rapid transit (BRT) system is one of the special features of the planned highway, which will involve construction of a dedicated lane for large-capacity buses to ease congestion.

The second stretch of 12 km will connect Likoni Road to James Gichuru Road junction on Waiyaki Way in Westlands, while the last section will run from James Gichuru Road to Rironi on the Nairobi-Nakuru highway. The road will also come with multiple interchanges at intersections on Popo-Kapiti, Lang’ata-Lusaka, Bunyala, Rhapta and James Gichuru roads.