Work on Buxar-Patna project to commence in AprilIllustrative image – not actual.

Work on four laning of the Buxar-Patna (NH-30 and NH-84) project is likely to start by April 2017, following clearance for land acquisition. Work on four laning of the Patna- Gaya- Dobhi (NH-83) project is also likely to speed up.

The project has been undertaken by National Highways Authority of India (NHAI).

Both the projects were stuck for the past couple of years due to an issue of land acquisition. Funds have been released for acquiring 70 percent of the land required for the Buxar-Patna project.

Of the total Rs 2,274 crore, Rs 1,028 crore has been disbursed till date for land acquisition in Jehanabad, Gaya and Patna districts. NHAI has already acquired 70 km of the 126 km Patna-Gaya-Dobhi project, and land acquisition process is underway for another 25 km stretch.  

In November 2014, NHAI entered into an agreement with IL&FS to execute the project.

 