Illustrative image – not actual.Madhya Pradesh Jal Nigam Maryadit is implementing Begamganj-Gairatganj multi-village rural water supply scheme in Raisen district of Madhya Pradesh.
The project received a nod from the SLEC in September 2014. The project remained under planning stage for almost three years.
Bids were invited from contractors to execute the project in April 2018 and in November 2018, Jay Varudi Construction was appointed as the contractor for the project worth Rs 84.87 crore.
Following this the work on the project began. As per the latest information available with Projects Today, work on the project was progressing as per the schedule and is expected to be completed by the end of May 2020.
The project received a nod from the SLEC in September 2014. The project remained under planning stage for almost three years.
Bids were invited from contractors to execute the project in April 2018 and in November 2018, Jay Varudi Construction was appointed as the contractor for the project worth Rs 84.87 crore.
Following this the work on the project began. As per the latest information available with Projects Today, work on the project was progressing as per the schedule and is expected to be completed by the end of May 2020.