Illustrative image – not actual.The incomplete work of breakwater construction in Azhikkal port for converting it into an all weather port is likely to resume soon. The work, awarded to Top Constructions Company, was suspended due to some legal obstacles.
The original plan was to construct two breakwaters at Azhikkal by February 2002. The state government has now renewed its interest in the project and the work is likely to commence during this month at an enhanced cost of Rs.22 crore against the original cost of Rs.16 crore. Under the new agreement the completion is targeted for March 2005.
The breakwaters stabilise the channel and increase the depth at the bar as shallow bar is the main hurdle for vessel traffic. The government has also allocated Rs.8 crore for extending the breakwaters by additional 200 meters.