Illustrative image – not actual.The Maharashtra State Electricity Distribution Corporation (MSEDCL), is likely to scrap the pending construction work of its 33 kV substation in Jalna due to delay in clearances.
The project, which is estimated to cost Rs 2.5 crore, has not yet received approval from the district collectorate.
In August 2012, the company had applied to the district collectorate for land to construct the substation. The project was to help supply uninterrupted electricity without voltage fluctuations. After receiving evaluation rates from the district collectorate, the power utility paid a sum of Rs 14 lakh to acquire the land, following which, work on the substation started.
Construction work came to a halt after the police training centre raised objections about the land acquisition process in February 2013.
The district collectorate then directed its land record office to reassess the land and submit a report within three days. However, the concerned department has still not submitted the report with the necessary information to the revenue department as well as to the district collector.
If the report is not submitted soon the MSEDCL may scrap the project.