Work nears completion on Bumbobi-Manafwa-Lwakhakha road projectIllustrative image – not actual.
The ongoing implementation of the Bumbobi-Manafwa-Lwakhakha road project in Uganda is nearing completion. Currently 92 percent of work on the project has been achieved.

The project is being undertaken by the Uganda National Roads Authority (UNRA). The work is expected to be completed by September 2020.

On 26 September 2016 UNRA signed a contract with China State Construction Engineering for upgradation of 44.5 km Mbale–Lwakhakha road with consultancy services of SGI JV.

The commencement order was issued in December 2016 and the initial set duration for the project was 24 months, but UNRA approved EoT of 261 days which led to the extension of the completion date to September 2020.

The road has been widened to a width of 10 mtr i.e. a carriageway made up of two lanes each measuring 3.5 mtr wide plus paved shoulders on either side of the road each measuring 1.5 mtr in rural areas and 2.0 mtr wide in trading centres.

An additional 3.5 mtr wide parking lane has been constructed in built-up areas and all existing culverts extended to a diameter of not less than 900 mm and proper concrete inlet/outlet structures installed for easier maintenance.

Upon completion, the road is expected to boost trade at Lwakhakha border post and promote trade, tourism and further integration in the East African countries.