The construction of new Pamban rail bridge connecting mainland with the pilgrimage island of Rameswaram in Tamil Nadu has gained momentum after the work suffered due to the lockdown.
The authorities are getting migrant workers from Jharkhand in batches and the work of sinking pile foundation on the seabed is underway. The project is being executed by Rail Vikas Nigam (RVNL). The rail bridge will entail an investment of Rs 248 crore.
The contract for constructing the bridge with a steel superstructure parallel to the century-old Pamban rail bridge was awarded in August 2019 and the work started in October 2019.
However, even as mobilisation of special equipment and materials for sinking 333 pile foundations was underway, the work had to be halted after the lockdown announcement.
The project envisaged construction of the bridge connecting Mandapam and Pamban railway stations. The new bridge would be 50 mtr away on the northern side of the old rail bridge.
Though initially the Indian Railways had proposed to replace the Scherzer’s span (two arms lifting) that allows ships to pass through the Pamban Channel at a cost of Rs 25 crore, it gave up the proposal and planned for the second sea bridge. The major difference the new bridge will have is a vertical lift span.
Instead of the 65.23 mtr long rolling lift span, the new bridge will have a vertical lift with a longer span of 72.5 mtr that will help an easier navigation of ships through the channel.
While the old bridge has an open foundation, the new bridge will have deeper foundation. The foundation will be around 30 to 40 mtr below the seabed. So far, work on 14 out of the 333 foundations has been completed.
The sub-structure has been designed for a double line on the new bridge. Though the second line on the bridge will come up when the doubling work is taken up on the section in future, the navigational span will be provided with double line.
Once the new bridge is constructed, the old bridge will be decommissioned and removed as it would be difficult to maintain the steel structure.
The project is scheduled to be completed by August 2021.