Illustrative image – not actual.The Banaras Hindu University (BHU) is constructing a residential complex in Varanasi district of Uttar Pradesh.
The project comprises four blocks -- two blocks with 80 flats (40 flats each) and two blocks G+10 floors with 200 flats (100 flats each) with modern amenities.
In August 2018, Winner Construction bagged an order worth Rs 34.08 crore from the Central Public Works Department (CPWD) for construction of teachers’ residential flats (80 nos), two blocks (40 each) including internal EI & fans, fire alarm system, firefighting system, lifts, DG set, CCTV & IP PBX system & substation at the project.
Further, in November 2018, Kashyapi Infrastructure bagged the order worth Rs 49.05 crore from CPWD for construction of 200 teachers residential flats (G+10), two blocks (100 in each block) including internal EI & fans, fire alarm system, firefighting system, lifts, DG set, CCTV & IP PBX system & substation at the project.
As per the latest development available with Projects Today, the work awarded to Kashyapi Infrastructure is progressing as per schedule. Moreover, the project will be ready by the end of July 2020.
The project comprises four blocks -- two blocks with 80 flats (40 flats each) and two blocks G+10 floors with 200 flats (100 flats each) with modern amenities.
In August 2018, Winner Construction bagged an order worth Rs 34.08 crore from the Central Public Works Department (CPWD) for construction of teachers’ residential flats (80 nos), two blocks (40 each) including internal EI & fans, fire alarm system, firefighting system, lifts, DG set, CCTV & IP PBX system & substation at the project.
Further, in November 2018, Kashyapi Infrastructure bagged the order worth Rs 49.05 crore from CPWD for construction of 200 teachers residential flats (G+10), two blocks (100 in each block) including internal EI & fans, fire alarm system, firefighting system, lifts, DG set, CCTV & IP PBX system & substation at the project.
As per the latest development available with Projects Today, the work awarded to Kashyapi Infrastructure is progressing as per schedule. Moreover, the project will be ready by the end of July 2020.