Work in progress for Sabarkantha's cattle feed plant in GujaratIllustrative image – not actual.

Sabarkantha District Co-operative Milk Producers Union is setting up a new cattle feed plant with a capacity of 800 tpd expandable up to 1600 tpd on 20 hrs basis at Hajipur village in Himatnagar, Gandhinagar district of Gujarat on a turnkey basis.

The scope of work entails design, engineering, supply, installation, testing and commissioning of the 11kV/433 V substation.

The work on the project commenced in October, 2022. 

As per the latest updates available with Projects Today, around 30 percent work on the project has been completed.

 