Work going on well at Golden Valley wind project in South AfricaIllustrative image – not actual.
The construction works are progressing well at the Golden Valley Wind project, in the Eastern Cape, South Africa. The 120 MW project is a BioTherm Energy development which comprises 48 2.5 MW goldwind turbines, a substation and 6.7 km of 132 kV overhead lines.

The current works on-site include installation of turbines and electrical works. The project is being undertaken by OptiPower which is responsible for full electrical balance of the plant including the substation, overhead lines, termination points, all reticulation works from the turbines to the substation and also commissioning of the plant once ready.

OptiPower was awarded the contract by Goldwind which is the engineering, procurement and construction (EPC) contractor. OptiPower had already completed the installation of power lines and the substation ahead of schedule while it is also making good progress to catch up on the reticulation works which had experienced delays earlier.

Moreover, OptiPower which began its scope of work in April 2019 is hopeful that the facility will be completed by the scheduled completion date of November 2020.

← All latest storiesBack to top →