Work commences on underground section of Janakpuri West-RK Ashram Marg corridorIllustrative image – not actual.
Construction work has commenced for an underground section of the Janakpuri West-RK Ashram Marg corridor, a part of the Delhi Metro Phase-4 project.
 
As part of the development work, construction of the D Wall along with the casting of tunnel segments of the 28.92 km long corridor has started. 
 
The construction work of D Wall at the Krishna Park Extension station of Delhi Metro along with the tunnel segments will be utilised for tunneling with TBM on 1.4 km long stretch between Janakpuri West and Keshopur. 
 
Moreover, the stretch which is nearly two km long will also have the Krishna Park Extension Metro station in between and 365 mtr cut along with a cover open ramp near Keshopur leading to the elevated section. 
 
The corridor between Janakpuri West and RK Ashram Marg Metro comprises 7.74 km underground lines. 
 
At the state-of-the-art casting yard that has been developed at Mundka, these tunnel segments are being cast. The casting yard will manufacture as many as 2,100 rings for the tunneling work. This work was awarded on engineering, procurement, and construction (EPC) basis in December 2019. 
 
Despite various constraints such as shortage of labourers and materials due to the imposition of the nationwide lockdown, the milestone could be achieved on time. For the same corridor, casting work of u-girders was started on 24 June 2020. 
 
The Janakpuri West-RK Ashram Marg corridor, which is a 28.92 km long corridor, is an extension of Delhi Metro’s Magenta Line. The corridor will come up with a total of 22 Metro stations.