Illustrative image – not actual.Prime Minister, Narendra Modi, inaugurated commencement of work at NTPC’s North Karanpura super thermal power plant on 21 August, 2014.
The foundation stone for the 3 x 660 MW thermal power project at Chatra, in Jharkhand, was laid on 6 March, 1999. However, due to some technical reasons the work could not commence.
Subsequently, on 20 February 2013, the Cabinet Committee on Investment (CCI), cleared the North Karanpura project and decided in-principle to restore the original coal linkage granted to the project.
Following which, the Coal Ministry restored the coal linkage on May 2013 with the stipulation that the coal supply would commence during the 13th Five Year Plan (2017-22).
Jharkhand will get around 230 MW from the North Karanpura power project. NTPC is already supplying about 298 MW power to Jharkhand from its various power stations.