Work commenced on GSPC's Pipavav power projectIllustrative image – not actual.

Work on the 700 MW (2X350 MW) combined cycle power plant at Pipavav in Amerli has commenced.

Speaking on the developments with ProjectsToday, a senior company official stated that, for the Rs.2,350 crore project being developed in two phases; work recently commenced on phase - I, which will set up a 350 MW power unit. GSPC Pipavav Power Company Ltd. the SVP company and promoter awarded the EPC contract to Bharat Heavy Electricals Ltd. for setting up the power unit - I of the project. During March, the company received all necessary clearances and achieved the financial closure for the project. The project is funded through 80 per cent of bank loans and 20 per cent internal accruals

 Work on the phase - I of the project is scheduled for completion by September 2010 and the entire project by December 2010.