Work begins on Son Nagar-Patratu third railway line projectIllustrative image – not actual.
The Rail Vikas Nigam (RVNL) has envisaged laying of Son Nagar-Patratu third railway line in length of 290.97 km in Bihar and Jharkhand.

The scope of work also includes electrification (railway electrification and general electrification work) and S&T works of Son Nagar-Japla (45.82 km) route of Mughalsarai division of East Central Railway.

In October 2018, Aarvee Associates Architects Engineers and Consultants bagged an order from RVNL for project management consultancy (PMC) services, construction of road bed, important, major & minor bridges and other works from Son Nagar (including) 411.83 km to Japla (including) 366.01 km with a total length of 45.82 km Package-1, and Japla (excluding) 366.01 km to Garhwa Road (excluding) 319.04 km with a total length of 46.97 km Package-2, in connection with the project.

In December 2018, Ashoka Buildcon in a joint venture (JV) with Story Tech Services bagged an order from RVNL for undertaking work in connection with the third line from Son Nagar to Garhwa Road in Dhanbad Division in two packages.

The above work will be undertaken from Son Nagar (including) from 411.83 km to Japla (including) from 366.01 km (total 45.82 km) in Mughalsarai division of Bihar & Jharkhand (Package- 1). The work is valued at Rs 384.70 crore. From Japla (excluding) from 366.01 km to Garhwa Road (excluding) from 319.04 km (total 46.97 km) in Mughalsarai division of Jharkhand. (Package- 2). The order value of the work is Rs 409.51 crore.

In a recent information shared with Projects Today, it was revealed that civil work was recently commenced with completion of the project scheduled for December 2022.