Illustrative image – not actual.Work on Sabarmati River Front Development project at Usmanpura in Gujarat, which was stalled in August 2006, has been restarted since the second week of March 2007.
Ahmedabad Municipal Corporation, which set up the Sabarmati Riverfront Development Corporation (SRFDCL) under the Companies Act, has begun the work on second phase of the project, defying the criticism that the project was badly designed and ran the risk of being washed away by floods unless major changes were implemented.
The team submitted its report in early-March 2007, suggesting two measures - a gauge to determine flood levels where the main canal of the Narmada crosses the Sabarmati; and dredging upstream of the Vasna barrage.
Of the estimated Rs.1,479 crore project cost, SRFDCL has so far spent around Rs.153 crore. As for land use, of the total 168 ha of land reclaimed, 80 per cent will be used by AMC for public use and the remaining will be leased out for private use.