The Konkan Railway Corporation (KRCL) is focusing on consolidation and expansion of its existing network.
The KRCL is working on doubling its entire konkan railway route of 739 km, with an initial project cost of Rs 11,000 crore and a completion period of five-seven years. The project cost may go upto Rs 14,000-15,000 crore.
The KRCL has taken up a pilot project of doubling the section between Roha and Veer, a distance of 49 km, at an estimated cost of Rs 295 crore. Track doubling will enhance the capacity 2.5 times and improve the average speed, besides enabling the KRCL to handle freight traffic.
Electrification of the entire konkan railway’s route will take 36 months, and will cost Rs 709 crore.