Work allocation for sea memorial to be decided by state govtIllustrative image – not actual.

The state government will decide on allocating work on the Chhatrapati Shivaji Maharaj memorial in the Arabian Sea in around 10 days. Work on the world’s tallest statue is expected to start in October 2017.

 

Three infrastructure majors had bid for it. Reliance Infrastructure lost in the technical evaluation; Afcons and L&T had quoted Rs 4,779 crore and Rs 3,826 crore respectively for the first stage. The first stage was expected to cost Rs 2,300 crore but the lowest bid was at a much higher cost of Rs 3,826 crore. If the project is awarded to the lowest bidder, work is expected to start after the monsoon season.

The Shivaji Maharaj statue, which has a 36-month completion period, will come up on a 15.96 ha rocky basalt outcrop in the Arabian Sea 1.2 km south west of Raj Bhawan. The statue will be 210 mtr tall as against the proposed 192 mtr. The total cost is estimated to be around Rs 3,700 crore for the two phases.