Widening of Mysore Road to be completed soon Illustrative image – not actual.

Work on widening of Mysore Road within city limits, is likely to be completed by end-October 2013.

 

The Karnataka Rural Infrastructure Development (KRIDL), is executing the widening work near the Mysore Road Satellite Bus Terminal. It has demolished around 40 petty shops outside the masjid and acquired about six private properties. The project on the two km stretch has been split into two, costing Rs 46.78 crore and 45.78 crore. It was slated for completion within 15 months of commencing the work.

 

The projects were delayed earlier, due to hurdles in removing utility lines, clearing trees and acquiring land. Completion of the project is scheduled by end-October 2013.