The Western Railway (WR) has undertaken regirdering of a bridge on Virar-bound fast corridor above Mithi river between Bandra and Mahim in Mumbai, Maharashtra, during the lockdown.

The bridge, whose work was pending for almost three years, is a steel girder bridge having six spans of 9.15 mtr and seven cross girder of length 5.8 mtr. This work required complete shutdown of traffic for eight hours on three consecutive days.

Two cranes of 200 tonne capacity, eight Farana cranes, 20 hydra and 18 JCB were deployed for the work apart from 40 track maintainers and contractual labour in each shift and dedicated team of Pway supervisors and officers. All pre-block activity was completed on 29 April 2020 and machinery was stabled at planned location.