Western Railway to build 39 bridges by March 2019Illustrative image – not actual.
The Western Railway (WR) is set to undertake the construction of 75 foot over bridges (FOBs), with 50 percent of them likely to be commissioned by March 2019.

WR has already constructed 10 bridges, of which two will be commissioned (opened for the public) by 31 December 2018. It aims to build 39 bridges by March 2019. The remaining bridges are likely to be ready by 2020.

WR is also looking at doubling of lines along 550 km in 2018.