Western Railway begins laying extra lines at Bandra TerminusIllustrative image – not actual.
The Western Railway has finally started work at Bandra Terminus-end for laying the fifth and sixth line after almost a decade.

The line meant for running long distance trains was missing between Santacruz and Mahim. With this line, there will be more scope for running suburban local trains. This will help in providing possibility of operating more services in future and improvise speed.

Work has also commenced for the sixth line at Bandra Terminus end. The initial work has been going for two months which involves laying tracks and overhead wires. This will be connected to the terminus to segregate long distance trains from both Mumbai Central and Bandra Terminus.

The additional lines are expected to be ready in the next two-three years. The Western Railway authorities had earlier spent Rs 10 crore to connect the fifth line.

This is part of Rs 918 crore Mumbai Urban Transport Project. So far, Rs 140 crore has been spent on the sixth line project.

The sixth line will give Western Railway a corridor--that is two lines--to run long-distance trains. Currently, Western Railway has a fifth line between Mumbai Central to Borivali but with a part missing between Mahim and Santacruz.

This fifth line is presently being used to operate over a few local trains between Andheri and Virar stations.