Western Railway awaiting clearance for high speed corridorIllustrative image – not actual.

The Western Railway is awaiting clearance from the Commissioner of Railway Safety for running trains on the 493 km Mumbai-Ahmedabad high speed corridor, at 130 kmph.


The Western Railway has already carried out successful trials on the corridor to run trains at 130 kmph. This will help reduce travel time by 30 minutes.


A Rs 1,100 crore plan has also been prepared and submitted to the Railway Board for approval to reduce travel time between the two cities by at least two hours. Under this project, the WR has plans to increase the speed of some trains on the corridor to 160 kmph. For this, improvement of tracks, barricading of vulnerable locations and regulating the overhead equipment (OHE), among other things will be undertaken.


After approval from the Railway Board, the entire exercise can be completed in a year.  Infrastructure improvement work on the high speed corridor can be completed in five to six months after the contractors are appointed.

Work will be done in two phases. In the first phase, only trains that run with LHB-designed fully air-conditioned coaches like Shatabdi, Duranto and Rajdhani will be able to attain the speed of 160 kmph, while the increase in speed in other trains will be done in the second phase.


India's first bullet train is also expected to run between Mumbai and Ahmedabad. For this project, the Japan International Cooperation Agency (JICA) is expected to submit its final feasibility study report by May 2015.