The Government of West Bengal has been
sanctioned Rs.43.50 crore for implementation of the Accelerated Power
Development Programme (APDP), following its signing of the Memorandum of
Understanding (MoU) with the Government of India on 5 May 2001. Of the total,
Rs.21.75 crore has been provided as grant, while the remaining Rs.21.75 crore
would be in the form of a loan. The process of the signing of the MoU was
actively pursued and monitored by the Minister for Power, Mr Suresh Prabhu.
Under the MoU, the Government of West
Bengal has committed itself to providing good quality uninterrupted power
supply at affordable rates. It has also committed itself to establishing commercial viability in the power sector so
that necessary investment needs of the sector can be met to cater to the
increasing demand for accelerating economic growth in the State.
Under the reforms programme agreed to
by the State Government, rural electrification would be completed to provide
electricity to all villages by March 2006. The distribution activity of the
West Bengal State Electricity Board (WBSEB) will be restructured into profit
centres and each centre will prepare its own commercial accounts/shadow profit
& loss account by 31 March 2002. The WBSEB shall undertake energy audit at
all levels to identify and reduce Transmission & Distribution (T&D)
losses to bring them to 20 per cent, by 2005.
The reduction in T&D losses will be
done in a time-bound manner with the following milestones :
·
Complete metering of
all EHV sub-stations and lines up to 11 KV latest by September 2001.
·
Complete metering to
all consumers by 31 December 2001.
·
Energy audit at 11 KV
level would be operational by 31 December 2001. On completion of energy audit,
assessment of real T&D losses shall
be drawn up and implemented.
·
Development of
effective distribution Management Information System.
The other points in the reforms
programme are achieving break-even in the WBSEB operations by March 2003, all
thermal power plants of WBSEB viz Bandel and Santaldih have been decided to be
provided under the West Bengal Power Development Corporation Limited. Timely
payment of subsidy required in pursuance of the State Government’s orders on
Tariff determined by the West Bengal Electricity Regulatory Commission (WBERC),
filing of timely tariff petitions and implementation of the orders of the
WBERC. Maintaining grid discipline, complying with grid code and availability
based tariff when it comes into force and carrying out the directions of the
Regional Load Despatch Centres. The State will also securities outstanding dues
of Central Public Sector Utilities (CPSU) as per the scheme approved by the
Government of India and after securitisation, it will ensure that CPSUs
outstanding dues do not exceed two months’ billing.
On its part, the Government of India
will provide funds from APDP for renovation, modernisation and upgrading of
thermal and hydro electricity units, upgrading of transmission,
sub-transmission and distribution network including energy accounting and
metering. WBSEB will be assisted in fully exploiting its hydro potential
through the development of projects by the State sector and joint ventures of
the Government of West Bengal and CPSUs. Adequate soft loans / funding for 100
per cent electrification of villages and hamlets will be provided by the
Ministry of Power through the Rural Electrification Corporation or other
agencies. The Power Finance Corporation will finance the State in meeting the
financial needs of the power sector in relaxation of normal conditionalities
relating to exposure limit, ROR and DSCR.
The implementation of the MoU will be monitored
every three months and will be for a period of five years, subject to annual
review.