Welspun-Gujarat plans debottleneckingIllustrative image – not actual.
Untitled

Welspun-Gujarat Stahl Rohren is planning a debottlenecking programme at its facility at Dahej in Gujarat, where it manufactures submerged arc welded (SAW) pipes.

An investment of Rs.25 crore is being entailed to enhance the output of plant, which currently operates at 70 per cent capacity.

The company is also awaiting approval from the Gujarat state government to develop a jetty at Dahej at a cost of Rs.5 crore.

Welspun-Gujarat is engaged in manufacture of pipes of diameter ranging 16 inches to 60 inches, with a capacity of 1,000 km. The demand for SAW pipes is expected to be around 17,000 km over the next five years, from the oil and gas sector. Of this, demand from the gas sector is likely to be around 13,000 km.

Pipelines provide a cheaper alternative to transport oil and gas with costs as low as Rs.1.30 per km. This is 50 per cent cheaper than rail and 70 per cent cheaper than road transport.