Illustrative image – not actual.Welspun Enterprises has received the letter of award (LoA) from PWD, government of Maharashtra, for road projects.
The project involves upgradation of roads/two-laning of roads/ two-laning of roads with paved shoulder under MRIP Package on hybrid annuity mode (HAM) Package No AM 2 under Public Works Circle, Amravati in Maharashtra.
The bid project cost is Rs 1,460 crore, with the project length 352.15 km across nine sub-packages.
The construction period is two years from the appointed date and O&M period is for 10 years after commercial operation date.
The company will receive 60 percent of the bid project cost from PWD during the construction phase, in five equal installments (adjusted for Price Index Multiple) which will be paid upon achievement of physical progress milestones.
The remaining 40 percent will be serviced through semi-annual annuity payments over 10 years period. In the O&M phase, the Welspun Enterprises will receive semi-annual O&M payments with the first year O&M payment being Rs 31.50 crore.
The company’s HAM portfolio, now consisting of seven projects, stands at over Rs 8,500 crore. Of these projects, five have achieved financial closure, and a firm sanction letter from lenders has been received for the sixth project.
The project involves upgradation of roads/two-laning of roads/ two-laning of roads with paved shoulder under MRIP Package on hybrid annuity mode (HAM) Package No AM 2 under Public Works Circle, Amravati in Maharashtra.
The bid project cost is Rs 1,460 crore, with the project length 352.15 km across nine sub-packages.
The construction period is two years from the appointed date and O&M period is for 10 years after commercial operation date.
The company will receive 60 percent of the bid project cost from PWD during the construction phase, in five equal installments (adjusted for Price Index Multiple) which will be paid upon achievement of physical progress milestones.
The remaining 40 percent will be serviced through semi-annual annuity payments over 10 years period. In the O&M phase, the Welspun Enterprises will receive semi-annual O&M payments with the first year O&M payment being Rs 31.50 crore.
The company’s HAM portfolio, now consisting of seven projects, stands at over Rs 8,500 crore. Of these projects, five have achieved financial closure, and a firm sanction letter from lenders has been received for the sixth project.