Illustrative image – not actual.
Welspun Enterprises has received a letter dated 1 September 2021 from the National Highways Authority of India (NHAI) declaring provisional commercial operation date (PCOD) with effect from 25 August 2021 in respect of the hybrid annuity model (HAM) project.
The project involves four-laning of Chikhali-Tarsod (Package-IIA) section of NH-6 from 360.000 km to 422.700 km in the state of Maharashtra.
With this event, the company is entitled to receive annuity, interest and O&M payments from NHAI every six months in accordance with the provisions of the concession agreement.
This is the fourth NHAI HAM project completed by the company, with a completion cost of approximately Rs 1,240 crore (with escalation).
The other completed projects are Delhi-Meerut Expressway Package-1 with a completion cost of Rs 896 crore, Chutmalpur-Roorkee-Gagalheri with a completion cost of Rs 1,108 crore and Gagalheri-Saharanpur-Yamunanagar with a completion cost of Rs 1,388 crore.
Thus out of the company’s total roads HAM portfolio of seven projects of around Rs 9,800 crore, four projects of Rs 4,600 crore have achieved PCOD/COD.
Moreover, the agreement with Soma Indus Varanasi Aurangabad Tollway with respect to undertaking the procurement and construction for six-laning of Varanasi-Aurangabad section of NH-2 from 786.000 km to 978.000 km in the states of Uttar Pradesh and Bihar, has come into effect, subject to compliance of certain conditions precedent there under.
The contract value for the company is Rs 2,336 crore (inclusive of GST) and the construction is to be completed in 24 months. With this project the company’s EPC order book is Rs 8,105 crore excluding work executed from 30 June 2021.