Illustrative image – not actual.Welspun Enterprises has acquired 49 percent stake in Chikhali-Tarsod road project for Rs 8.33 crore.
The project envisages four laning of Chikhali-Tarsod (Package-IIA) section of NH-6 from 360.000 km to 422.700 km in Maharashtra. The road project will be implemented on hybrid annuity mode (HAM).
The company has an option to acquire the remaining 51 percent stake as and when the regulator National Highways Authority of India (NHAI) permits at a fixed consideration of Rs 86.7 million.
The project will have 40 percent financial support from NHAI. The debt component is estimated to be 48 percent of the project cost; and as sponsor, the balance will be funded by Welspun Enterprises. The EPC contract of the project will be executed by Welspun.
The project entailing investment of Rs 9.09 billion will spread over 62.7 km. The project will be executed in a period of 910 days. The operation period will be 15 years from the commencement date.
The project will incur an expenditure of Rs 40.1 million in the first year of operation and maintenance (O&M) period.
The project will get expected fund commitment of Rs 1.13 billion from sponsors.