West Bengal Power Development Corporation (WBPDCL) has planned to add 1,120 MW of fresh power capacity to its existing 2,900 MW by 2007. This is being done with a view to meeting increased power requirements of the state.

Currently, the peak demand in West Bengal is about 4,000 MW and this is likely to go up to over 5,300 MW in the coming years.

WBPDCL has been entrusted with several projects, mainly Bakreswar Thermal Power Project (Units IV and V of 210 MW each), Sagardigh Thermal Power Project (Units I and II of 250 MW each) and Santhaldih Thermal Power Station (Unit V of 250 MW).

West Bengal chief minister, Mr Buddhadeb Bhattacharjee laid the foundation stone of the Sagardighi Project in Murshidabad district on Sunday, 8 February 2004.

WBPDCL is the second largest power generating company in the state, after NTPC, and meets 60 per cent of the total energy demand of the state, and accounts for 90 per cent of the power generated by the West Bengal State Electricity Board.