WAPDA is setting up six hydel power projectIllustrative image – not actual.

The Water and Power Development Authority (WAPDA) is working on six hydropower projects with cumulative generation capacity of about 1,444 MW, out of which five projects were in construction phase, while the remaining was in the final stage of its detailed engineering designs. The company will spend around Rs 138.995 billion to execute the six projects for stabilising energy and the hydropower sector in the country for fiscal year 2012-2013. 

It is executing on priority the 969MW Neelum-Jhelum, 130MW Bubeer Khwar Kohistan, 121MW Allai Khwar, 100MW Jinnah Hydropower, 22MW Jabban Hydropower, and Chitral KP projects to meet the increasing demand of electricity in the country. Rs 16.324 billion had been set to build the Bubeer Khwar Kohistan power plant that would produce 130MW. 
 
Source: DailyTimes