Illustrative image – not actual.
WABAG has bagged a contract worth Rs 420 crore from the City and Industrial Development Corporation of Maharashtra (CIDCO) for a water treatment plant (WTP) with a capacity of 270 MLD at Jite in Raigad distict of Maharashtra.
The work entails design, build and operation (DBO) of a WTP, including a clear water pumping station. The proposed WTP will treat the water from the Hetwane dam before pumping it to the existing master balancing reservoir (MBR) at the Vihal location for further distribution. The project will cater to the future water demand in Navi Mumbai.
The project is expected to be completed within 42 months from commencement date, and operation and maintenance (O&M) will be carried out for 15 years.