Vodafone to commission Airoli data centre in 2015  Illustrative image – not actual.

Vodafone is planning to commission its data centre at Airoli, Navi Mumbai, in Thane district of Maharashtra, by March 2015.

 

The company is setting up the centre at an investment of Rs 700 crore. The project comprises four blocks of G + 3 floors. Around 50 per cent of the work is already completed.

 

Of the four blocks, the first block is expected to be completed by May 2014.

 

Vodafone has appointed Supreme Infrastructure India to construct the data centre building. The latter is expected to commission the construction work by September, 2014. 

 

ABB is the electrical contractor for the project, while Honeywell India and ETA are the sub contractors.

 