The multi-crore Vizhinjam International Seaport project failed to attract any bidders on 20 February.

 

The deadline for prospective private partners to place their price bids was on 20 February, 2015. However, none of the three firms/consortiums that had purchased the bid documents put in an appearance at the office of the Vizhinjam International Seaport (VISL).

 

The UDF government has now extended the deadline to March 25 for placing the bids. The government will also call a meeting of the bidders shortly.

 

The government had shortlisted five firms/consortiums, but only three -- Essar Ports; a consortium of Srei Infrastructure and OHL; and Adani Ports -- had purchased the RFP documents. The other two, Gammon Infrastructure Projects and a consortium of Hyundai and Concast Infratech, had not purchased the documents.

 

Recently, the centre agreed to provide Viability Gap Funding (VGF) to the extent of Rs 800 crore, the first in the country for a port project.

 

On 4 December 2013, the government floated tenders for selecting a private partner, making it the fourth instance for this particular project since 2007.

 