Vizag Port connectivity project on trackIllustrative image – not actual.

The Rs.80 crore project aiming to offer road connectivity to the Visakhapatnam Port is likely to be completed ahead of schedule.

It may be recalled that the Vizag Port Trust and National Highways Authority of India (NHAI) have formed a special purpose vehicle, Visakhapatnam Port Road Co Ltd, to implement the project.

Construction work for this 12-km four-lane roadway connecting the Vizag port to NH-5 was awarded to Vizag-based MVR & Sons, on 17 June 2002.

According to the contracting company, fifty per cent of the physical work has been completed and the project is likely to be completed much ahead of the scheduled completion date of 16 December 2004.

NHAI has appointed LEA Associates South Asia Private Limited as a supervision consultant for this project.