Visakhapatnam Steel Plant taken up clean development mechanism projectsIllustrative image – not actual.

Visakhapatnam Steel Plant (VSP) has taken up six clean development mechanism (CMD) projects to generate 120 million unit power by using waste gases in Visakhapatnam, Andhra Pradesh.

Under the CDM projects, VSP will take up works like installation of energy efficient air separation unit, pulverised coal injection in blast furnaces -1 and 2, waste heat recovery from special bar mill-2, waste heat recovery from wire rod mill-2 and billet caster in steel melting shop-2. These initiatives will reduce carbon dioxide emissions by more than 854,000 tonnes annually. The company will invest Rs 677 crore to set up a power plant with commissioning slated for September 2013.