Illustrative image – not actual.Gas
Authority of India (GAIL) has stated that it would commission its
Visakhapatnam-Secunderabad LPG pipeline in Andhra Pradesh by June 2003. The 600
km pipeline would have an LPG carrying capacity of 1.1 million tonnes per
annum, and would cost around Rs.500 crore. The pipeline would have an
offloading facility at Vijayawada, and would cater to the needs of power plants
in the region.
Meanwhile,
on 21 August 2001, GAIL also initiated work on the 10.5 km sub-pipeline to Samalkot
from Kakinada junction to provide 1 million cubic metres of gas per day to the
BSES power plant at Samalkot. The pipeline project, costing Rs.25 crore, would
be completed by October 2001.
It
may be recalled that on 20 August 2001, GAIL commissioned the
Tatipaka-Kondapalli pipeline for the Lanco Kondapalli Power Project.
GAIL
is presently supplying 62 million cubic metres of gas per day throughout the country,
as against the demand of 90 million cubic metres.