Visakhapatnam power project may be revivedIllustrative image – not actual.

Hinduja National Power Corporation is reportedly planning to revive the 1,040 MW Visakhapatnam power project and has conveyed the same to the government. The project was stalled after National Power backed out and financial institutions cancelled all loans sanctioned citing high project cost and delays in implementation.

Power from this project is estimated to cost Rs.5.8 crore per MW as against Rs.3.6 crore per MW for Simhadri thermal power project. The government has reportedly asked HInduja group to match power tariff provided by Simhadri.

The project was earlier planned with Mission Energy however differences over day to day management led to withdrawal of Mission Energy from the project.

Hyundai Engg & Construction had already commenced civil contract works and $50 million (Rs.230 crore) was spent on the project. Hinduja group has also reportedly agreed to implement Vizag power project on its own.