Visakhapatnam Port Trust to set up solar power plantIllustrative image – not actual.

The Visakhapatnam Port Trust (VPT) plans to commission a 10 MW solar power plant by March 2016 in two phases.

The first phase will involve setting up a 2 MW solar power plant by 15 January 2016, whereas the remaining 8 MW will be commissioned by 20 March 2016.

The contract for the project has been awarded to Jakson Engineers, Noida, who will also maintain the power plant for seven years. The total project cost is estimated at Rs 60 crore, including annual maintenance cost of Rs 2.5 crore.

The solar plant will supply around 150 lakh units of power to VPT and the surplus will be given to public-private partnership (PPP) operators.