Visakhapatnam port fertiliser berth delays due to land issues  Illustrative image – not actual.

The fertiliser berth project, which is coming up at the Visakhapatnam port, is being delayed as the port administration and Vizag Agriport, the concessionaire for the project, are still deciding the issue of taking possession of the land required for the project.

 

The fertiliser terminal has a capacity of six million tonne and was awarded to the Vizag Agriport, a JV between ALBA, port operator (74 per cent equity) and IL&FS Maritime (26 per cent).

 

While the port blames Vizag Agriport for the delay in taking possession of the land, the latter counters that it is the responsibility of the port to hand over the land required for the project. ALBA is again a JV between Mumbai-based ABG Ports and Louis Dreyfus of France.

 

In a recent communication to the Ministry of Shipping, the Visakhapatnam port trust held that the fertiliser mechanisation project awarded to ABG at Eastern Quay-7 (EQ-7) has been going on at a very slow pace.

 

Inspite of the concession agreement being signed in May 2012 and the concession awarded in July 2013, ABG has not taken possession of the land, requesting for waiver of bank guarantee / security deposit for land allotment.

 

On the other hand, Vizag Agriport, the proponent of the project, maintains that according to the agreement, it is the responsibility of the Visakhapatnam port to hand over the land. It further holds that the company has fully completed the conditions precedent (CPs) and the port has already given it the Date of Award.

 

Vizag Agriport is ready to execute the project, if land is handed over to them.

 