Visa Steel's Orissa project on trackIllustrative image – not actual.

Visa Steel will fully commission its 4 lakh tpa coke oven plant in Orissa by September 2006, it is learnt. The company already commissioned 1 lakh tpa of capacity in March 2006.

The coke oven plant is part of the Rs.4,500 crore integrated steel complex coming up at Kalinganagar Industrial Complex in Orissa. Other components of the project include a 50,000 tpa ferro chrome plant, a 3 lakh tpa sponge iron plant, a 50 MW heat recovery power plant and a 0.5 million tpa stainless steel plant. The project is being financed through a debt-equity ratio of 65:35. The company will invest Rs.1,146 crore over the next 18 months on the sponge iron, steel and power plant projects.

For coal requirements, the company has been allotted the Patrapara coal block in Talcher, which is would share with seven other companies.

The company has also applied for iron ore mines and also for 500 acres of additional land to take care of future capacity expansions. Both the applications are currently under the state government's consideration.

Also See:

Visa Steel to raise Rs.1,136 crore for expansion (21-Feb-06)

← All latest storiesBack to top →