Visa Steel's coke unit by March 2006Illustrative image – not actual.

Visa Steel's 4 lakh tpa coke oven project is scheduled for commissioning in March 2006, with full production targeted for June 2006.

The Rs.160 crore coke oven project is part of Phase I of Visa's fully integrated 1.5 million tpa integrated steel and stainless steel project coming up at Kalinganagar Industrial Complex in Jajpur district of Orissa at a total cost of Rs.2,500 crore.

In Phase I of the project, steel capacity of 0.5 million tpa would be attained by 2007, and full capacity would come on stream by 2010. In March 2005, a 2.25 lakh tpa blast furnace costing Rs.96 crore was commissioned. This furnace that would produce pig iron is also part of Phase I of the project.

Visa has applied for coal blocks and iron ore mining rights. One coal block at Patrapara in Talcher district of Orissa has been allotted to the company.

The overall plans of the company also include setting up of two power units of 25 MW each, running on waste heat. The first unit will be commissioned by December 2006 and the second, by March 2007.