Work on overlaying Virudhunagar-Kanyakumari four-lane national highway (NH) for a stretch of 180 km is likely to commence before the beginning of May 2021.
The milling could be planned for 1.5 km a day whereas relaying can be done for 1.2 km a day. Also, work on studs, thermoplastic painting and road furniture is also planned. The work on the project is likely to be completed by 20 October 2021.
The National Highways Authority of India (NHAI) has targeted planting 583 trees for every one km to improve green cover along national highways. But this is subject to availability of vacant places.