Illustrative image – not actual.Larsen & Toubro has sought more time to decide on its equity participation in the Vijayanagar power project, following the promoter, Karnataka Power Corporation Ltd’s (KPCL) refusal to accept its pre-conditions to pick up equity in the project.
One of the pre-conditions set by L&T was award of
the EPC contract to it. When this was not accepted by KPCL, L&T insisted on
being given the first right of refusal at the time of the competitive bidding
process for the EPC contractor. This too was not acceptable to KPCL.
KPCL prefers to abide by the guidelines of the
Electricity Regulatory Commission, which entails that the EPC contractors
should be selected entirely through the competitive bidding route.
KPCL proposes to set up the project with a total capacity
of 720 MW in two phases in Karnataka, using naphtha as fuel.
It may be recalled that the original plan envisaged a
capacity of 500 MW with gas as fuel.