Illustrative image – not actual.The under-construction Versova–Bandra Sea Link has achieved around 32 percent overall civil progress and nearly 30 percent financial progress after close to seven years of development, according to latest project updates.
Originally awarded in 2018 to Reliance Infrastructure and its joint venture partner Astaldi for an EPC contract worth Rs 7,000 crore, the project was scheduled for completion within 60 months from June 2019. However, execution was significantly delayed as the consortium failed to achieve on-ground progress. Subsequently, Reliance Infrastructure exited the project by transferring its stake, after which Webuild (Astaldi Group) took over execution in partnership with APCO Infratech. Current construction status shows steady advancement in marine infrastructure works. Piling has reached 46.73 percent, bent piles 43.93 percent, pile caps 32.64 percent, and pier works 37.64 percent. More complex components like pier caps stand at 19.71 percent, while precast segment production is at 24.80 percent.
Simultaneously, temporary access bridges and marine foundations are being developed, with multiple construction fronts active across sea and land sections. The project remains a key infrastructure link intended to improve connectivity between Mumbai’s western suburbs.