Illustrative image – not actual.GMR Rajahmundry Energy (GREL), is likely to achieve commercial operation declaration (COD) at the Unit I 384 MW of its combined cycle power project (CCPP), located near Rajahmundry, in the East Godavari district of Andhra Pradesh, by October 2011.
The second 384 MW unit is likely to be commissioned in January 2012. The synchronisation of gas turbine generators for the two units is targeted for April and July 2011.
GREL has already obtained all the statutory clearances for the project and attained financial closure in September 2010, with IDBI as the lead banker. It has also signed the gas transmission agreement with GAIL for the supply of the required fuel.
Besides, the EPC contract for the CCPP has been given to L&T and the power evacuation network to SEW Infrastructure, for likely completion in April 2011.