Velodrome project to be completed by end of March 2017Illustrative image – not actual.

The officials of the Sports and Youth Services Department noted that the Velodrome project for cyclists near Bhutanal Tanda, in Bijapur district, Karnataka, would be completed by the end of March 2017.

The project, which was pending for years, finally began on 28 June, 2015, when the former Sports Minister, Abhayachandra Jain, laid the foundation stone for it.

However, the 333 mtr track project, which was supposed to be completed within a year, was delayed as the contractor for the project did not consult technical experts from the Cycling Federation of India (CFI) in implementing the various works for the project.

 