Illustrative image – not actual.Lanco Green Power Pvt Ltd (LGPPL) achieved financial closure for its 70 MW Budhil hydroelectric project in Himachal Pradesh with the signing up of loan documents with ICICI Bank, the term lender to the project.
The hydropower plant is located on Chamba-Bharmour Road with its dam site near village Thalla and power house on the right bank of river Ravi near village Kainduta, at about 66 km and 51 km upstream of Chamba respectively. It envisages utilisation of water of Budhil nallah through a gross head of +252 m for generation of 70 MW of power.
The Lanco group also reached financial closure for the projects implemented by Vamshi Hydro Energies Pvt Ltd which is as follows
The projects implemented by Vamshi Industrial Power Ltd also achieved financial closure which is as follows:
All the projects are of 5 MW capacity with State Bank of India being the lead financier for each of them.