Illustrative image – not actual.The 540 (4x135 MW) coal fired power unit of the Raipur based Vandana Vidhyut is likely to achieve financial closure by January 2008. The power plant coming up at Katogara in Korba district of Chhattisgarh entails an investment of Rs.2,150 crore.
At present, the company is in the process of land acquisition which is likely to be completed by March 2008. The project will spread over 645 acres of land. The power project has already received techno-economic clearance; environmental and CEA clearances are expected by mid-February 2008. M. N. Dastur & Company is the consultant.