Vallarpadam terminal faces hurdlesIllustrative image – not actual.

The International Container Transshipment Terminal (ICTT) at Vallarpadam in Kerala is unlikely to be operationalised as per its scheduled time due to slow pace of the road connectivity project. The proposed ICTT is expected to commence operations by April 2010.

The road connectivity between the terminal and NH 47 is vital to the project as around 80 per cent of the container traffic is expected through road in the initial stage.

The work is still running behind schedule due to various reasons and is unlikely to be ready for the four lane traffic by March 2010. So far, only 50 per cent of the road work has been completed.

A recent strike by tipper lorry workers and now shortage of river sand are some of problems that are hindering the progress of work for the road. Moreover, the slow progress in the linkage of bridges on the proposed road is a major hurdle as the two-lane traffic can be provided only when this is complete.

The Cochin Port Trust has, however, assured DP World that the two lane traffic is likely to be ready within the deadline. According to the contract between CPT and DP World, the former has to pay a huge compensation if the rail and road connectivity and allied infra facilities are not ready by March 2010.