Vadinar refinery by June 2006Illustrative image – not actual.

Essar Oil has announced that its 10.5 million tpa petroleum refinery coming up at Vadinar in Jamnagar district of Gujarat will be completed by June 2006.

The company has also stated that the project has achieved financial closure and that 70 per cent construction was complete. The refinery's capacity would be scaled up to 12 million tpa by June 2007.

Meanwhile, the company also plans to set up 5,000 retail outlets in the next few years. Currently, Essar has licence to set up 1,700 retail outlets out of which 250 are already in place.

ProjectsToday adds:

In February 2005, certain sections of the press had carried reports of Essar Oil's Vadinar refinery having attained financial closure. However, in a communication sent to the National Stock Exchange, the company clarified that it had NOT achieved financial closure, although it maintained that work on the project site was progressing satisfactorily. Essar Oil's current announcement of having attained financial closure is yet to be confirmed.

← All latest storiesBack to top →